In South Carolina the choice among CMAR, design-build and design-bid-build turns on one question: how finished is the design when the owner hires the builder? Design-bid-build awards construction after the design exists. CMAR lets the owner sign with a builder earlier. Design-build puts design and construction in one contract. For procurements governed by the state code, the governmental body must document its reasons for selecting the delivery method.

CMAR vs design build vs design-bid-build: what is the difference in South Carolina?

Design-bid-build, CMAR and design-build are three of the delivery methods South Carolina authorizes for public infrastructure facilities. They differ in how many contracts the owner signs, how the builder is selected, when a construction contract can be signed and when bonds are due. The table sets them side by side.

The wording below comes from the state's Consolidated Procurement Code, Title 11, Chapter 35. Section 11-35-3005 states: "The following project delivery methods are authorized for procurements relating to infrastructure facilities".

Design-bid-buildConstruction management at-risk (CMAR)Design-build
Definition (11-35-2910)a project delivery method in which the governmental body sequentially awards separate contracts, the first for architectural and engineering services to design an infrastructure facilitythe owner awards separate contracts for design and to a construction manager at-risk for construction and construction management servicesa project delivery method in which the governmental body enters into a single contract for design and construction of an infrastructure facility
How SC procures it (11-35-3015)design-bid-build construction is procured by competitive sealed biddingContracts for construction management at-risk must be procured as provided in either Section 11-35-1520 (Competitive Sealed Bidding) or Section 11-35-1530 (Competitive Sealed Proposals).Design-build uses competitive sealed proposals or competitive negotiation.
When the construction contract can be signedthe second for construction of the infrastructure facility according to the designA contract with a construction manager at-risk may be executed before completion of design.a single contract for design and construction
Bond timing (11-35-3030)For state competitive sealed bidding over one hundred thousand dollars, bid security of at least five percent accompanies the bid. The construction contract must require performance and payment bonds or permitted security; confirm delivery deadlines in the solicitation and contract.CMAR solicitations may defer bonds during preconstruction or designneither design nor construction of a designated portion may begin before delivery of its required bonds or security

Read the table by row. The definition row shows the contract count. The signing row shows when the builder joins. The bond row shows when the owner gets security. Bihn Construction delivers under all three, plus preconstruction and construction management agreements, so the page compares the methods without favoring one.

Can a contractor be hired before the design is finished?

Yes. CMAR permits a construction-manager contract before design is complete, while design-build places design and construction under one contract. SC Code 11-35-2910 provides that "A contract with a construction manager at-risk may be executed before completion of design." Under design-bid-build the second contract is for construction "according to the design", so the builder joins once the design is done.

That timing is the point of CMAR. The builder prices, schedules and reviews constructability while the drawings are still changing. Under CMAR, Bihn commits to a Guaranteed Maximum Price at a defined design milestone, carries the cost risk, and provides open-book accounting. Joe Martin owns the preconstruction phase: estimating, scheduling, value engineering, and constructability review. Our construction manager at risk service page covers how that works on an owner's project.

Design-bid-build is the better fit when the drawings are complete and the owner wants sealed price competition. Bihn's design-bid-build service prices the finished design. For owners who want one contract for design and construction, our design-build service coordinates architects, engineers and trades from the first sketch.

When do bonds come due under each method?

For state design-bid-build competitive sealed bidding on construction contracts over one hundred thousand dollars, bid security must be at least five percent of the bid. On CMAR work, CMAR solicitations may defer bonds during preconstruction or design, but construction of a designated portion may not begin until the appropriate bonds or security have been delivered to the governmental body.

Design-build runs on a stricter clock. Under SC Code 11-35-3030(2), neither design nor construction of a designated portion may begin before delivery of its required bonds or security. For the full bid-day rules, including the subcontractor list and bid openings, read our guide to South Carolina public construction bid requirements.

Delivery method selector

Use the table to match an owner's situation to a method. The basis column names the code section behind each row. Every row also sits under SC Code 11-35-3010, which requires the governmental body to state in writing the facts and considerations behind its choice. The code puts it this way: the governmental body "shall state in writing the facts and considerations leading to the selection of that particular method". The State Engineer's Office "has ten days to review the data submitted by the governmental body".

Owner situationMethodSC Code basis
The design is complete and the owner wants sealed price competition on a full set of documentsDesign-bid-build11-35-3015 (competitive sealed bidding) and 11-35-3030 (bid security); reasons recorded per SC Code 11-35-3010
The owner needs a builder on the team while the drawings are still changingCMAR11-35-2910 (a CMAR contract may be executed before completion of design); reasons recorded per SC Code 11-35-3010
The owner wants one contract and one accountable team for design and constructionDesign-build11-35-2910 (single contract) and 11-35-3015 (competitive sealed proposals or competitive negotiation); reasons recorded per SC Code 11-35-3010
The owner expects to settle the design in phases and wants bonds tied to each designated portionCMAR or design-build11-35-3030(2) (bonds for designated portions); reasons recorded per SC Code 11-35-3010

The selector covers state procurements. Counties and cities follow their own rules. Under SC Code 11-35-5320, all political subdivisions of the State shall adopt ordinances or procedures embodying sound principles of appropriately competitive procurement. Read the owner's solicitation before assuming which method applies.

How does a CMAR invitation read in practice?

Two Clemson University invitations on the SCBO site show the method in public use. The first requests construction management at-risk services for the Littlejohn Coliseum and Swann Pavilion Renovation.

South Carolina Business Opportunities, or SCBO, is described as "a live database for goods, services, information technology and construction needs of state and local government." You can read the Clemson University invitation for Littlejohn Coliseum, as posted on SCBO in full. Its header reads "PROJECT NAME: Littlejohn Coliseum and Swann Pavilion Renovation".

A second Clemson University invitation requests construction management at-risk services for the Williamson Road Parking Garage. An invitation states its scope and cost range up front, so a builder can judge the fit before responding. Neither invitation is a Bihn project.

Working with Bihn under any of the three

Bihn Construction's delivery methods are Design-Build, Design-Bid-Build, Construction Manager at Risk (CMAR), Preconstruction, Construction Management. Our capabilities and prequalification page lists what we send for an owner's prequalification file, and our services overview shows each delivery method in full.

Send drawings, an RFP or an invitation to bid through the project inquiry form or to welcome@bihnconstruction.com. Mike Reda is the first call for new project inquiries. You can also call (864) 305-5307.